Horizontal Directional Drilling
OFFER
- max . pipe diameter Ø = 1400mm
- max . drilling length Lmax = 2900m
|
Drilling Rig |
SCOPE OF WORK |
GEOLOGICAL CONDITIONS (soil category) |
|---|---|---|
|
Prime Drilling PD250/90RP |
L max.= 2900m, Ø max. = 1400mm |
I - VII |
|
Herrenknecht HK100C |
L max.= 1800 m, Ø max. = 1200mm |
I - VII |
|
American Augers DD100B |
L max.= 1200 m, Ø max. = 1000mm |
I - VII |
|
Vermeer Navigator D75x100 |
L max.= 800 m. Ø max. = 600 mm |
I - VII |
|
Vermeer Navigator D36x50 II |
L max.= 300 m, Ø max. = 600 mm |
I - IV |
| Vermeer Navigator D24x40a | L max.= 300 m, Ø max. = 400 mm | I - IV |
|
Vermeer Navigator D24a |
L max.= 150 m, Ø max. = 315 mm |
I - IV |
|
Vermeer Navigator D7x11a |
L max.= 60 m, Ø max. = 160 mm |
I - IV |
TECHNIQUE
- Stage I- Pilot drilling
.jpg)
- Stage II- Reaming
In this part of the works , it expands previously developed a pilot hole for installation pipe with a diameter assumed . The ground is mold by using various types of reamers to a diameter greater by 20 % - 50 % of the diameter of the pipe which is installed in the borehole ( not the values are fixed but closely related to the geological conditions at the work site ) . The cutters are formed as a result of reaming geological layers and emptied from the bore by drilling fluid .
.jpg)
- Stage III - Installing pipe into the hole
The final stage is a installing productive pipe in borehole- pulling pipe into hole by using special pulling head. Cutters is the remains of excavated material and polymer additives in the scrubber minimize friction between the pipe and the wall of the borehole , which facilitates the installation of the pipe in the hole by reducing the axial forces (torque ) and tangential forces.
Guided Pipe Jacking
- Stage I- Pilot drilling
.jpg)
- Stage II- Reaming and pushing steel casing
.jpg)
- Stage III- Pipeline installing and casing removing
.jpg)
Microtunneling
NAWITEL's offer includes execution by using microtunnel method for building pipelines made of: stoneware pipes , concrete , polymer concrete , GRP and others.
• L max . = 150 m , diameter DN400 ( DZ 560 ) to DN1000 mm ( DZ1099 ) set to microtunnel Herrenknecht AG
Mikrotunnelling is often referred to as a highly automated and computerized method of trenchless construction of underground pipelines, technology, single-stage hydraulic jacking. This method involves using a tunneling/drilling shield while the drill pipe are jacking,when the process is almost totally automated. It is a technology for single-step execution pipelines. The control is possible by jacking the special articulated head, the position of which is changed by means of hydraulic control cylinders.
The process of pushing pipes is measured using the laser beam, which ensures a very high accuracy in the hole. Beam laser placed in the rear part of the initial excavation is received by the electronic receiver equipped with a target plate, here are transmitted to the control station the necessary information about the position of the axis of the drill head, where they are processed and recorded. Control of the entire process microtunnelling is done with the help of a computer. In this method it is possible to embed pipeline, whose route runs along the arc.
(1).jpg)